Construction Contract Administration

Federal Acquisition Regulation (FAR) 36.211(b) requires agencies provide description of policies and procedures that apply to definitization of equitable adjustments for change orders under construction contracts and data on the time required to definitize equitable adjustments for change orders under construction contracts.

The Department of the Interior does not have any supplemental policies and procedures in regards to definitizing equitable adjustments for change orders under construction contracts.

The table below contains data, as it is made available, regarding the definitization of equitable adjustments for change orders under construction contracts.

Time to definitize after receipt of an adequate change order definitization proposal under construction contracts Number of change order proposals definitized under construction contracts FY23-FY25 (to date, updated quarterly)
 30 days or less  34
 31 to 60 days  13
 61 to 90 days  6
 91 to 180 days  3
 181 to 365 days  7
 366 or more days  0
 After completion of contact performance via a contract modification   addressing all undefinitized equitable adjustments received during   contract performance  19

Data only includes contracts over the Simplified Acquisition Threshold (SAT). 